After two investigations in 2020, the Nuclear Regulatory Commission (NRC) determined FPL employees engaged in deliberate misconduct during 2019.
The first investigation confirmed three mechanics falsified information in a work order associated with the inspection and maintenance of a safety- related check valve.
Following a pre-decisional enforcement conference with FPL on March 3 and a separate review of documents provided by FPL, the NRC determined these actions merited a Severity Level III violation under the agency’s enforcement policy. FPL accepted the violations during the conference, including the willful aspects.
Details of the violation and proposed civil penalty were issued to FPL on April 6. FPL has 30 days to pay the fine or contest the notice of violation.
The violations did not result in an increased risk to the public, and FPL has initiated corrective actions to prevent a recurrence of the events leading to the violations.