In one of the most significant accomplishments to date, open vessel testing wrapped up for Unit 3 at Georgia Power’s Vogtle 3 & 4 nuclear expansion project near Waynesboro, Georgia.
Open vessel testing, which is a major systems testing milestone, successfully demonstrates how water flows from the key safety systems into the reactor vessel ensuring the paths are not blocked or constricted. It also prepares Unit 3 for cold hydro testing and hot functional testing –critical tests required ahead of initial fuel load. The milestone confirmed the pumps, motors, valves, pipes and other components of the systems function as designed.
Plant operators performed quite a few of the tasks associated with open vessel testing from the Unit 3 main control room, which began operating in December and has staff working there around the clock.
“The completion of Open Vessel Testing is a major accomplishment for the project and brings us an important step closer to generating electricity for our customers as we continue the transition from construction toward system operations,” said Vogtle 3 & 4 Construction Executive Vice President Glen Chick.
Significant progress continues at the site with the project now 85 percent complete, and direct construction of Unit 3 now 90 percent complete. Major milestones achieved in recent weeks include the placement of the Unit 4 polar crane and containment vessel top, signifying all major lifts inside the containment vessels for both units are now complete.
Additional milestones achieved over the last few months include:
- Operation of the Unit 3 main control room: Operators begin monitoring and controlling the technology and equipment essential for testing the unit’s systems and safely starting the plant.
- Placement of the Unit 3 shield building roof: The two-million-pound roof covers the top of the shield building, which provides an additional layer of safety around the containment vessel and nuclear reactor to protect the structure from any potential impacts.
- Final concrete placement inside the Unit 3 containment vessel: Completing this milestone is an important step that allows for the installation of machinery used to load fuel into the unit.