By Gregory Hale
Unplanned maintenance was being conducted on the Line 4 immersion freezer at the time of a deadly nitrogen leak that left six workers dead and 12 others injured at a Gainesville, Georgia poultry plant Thursday, federal officials said Monday.

The unplanned maintenance points toward tools located on the ground around the leaking equipment. In addition, major portions of the liquid nitrogen system at the Foundation Food Group poultry processing center ended up installed and commissioned in the last 4 to 6 weeks on Line 4 in Plant 4 at the facility.

Prior to the installation of this system, the company used a different type of freezing equipment, which was ammonia-based. This equipment is still collocated on Line 4 adjacent to the cryogenic system and has not yet been removed. The approach of using liquid nitrogen ended up introduced to Plant 4 in 2020, as it is also being used on Line 2 in Plant 4.

At 10:15 a.m. Thursday multiple 911 emergency calls reported an incident at Foundation Food Group’s Prepared Foods Division, Plant 4, in Gainesville, GA, said Dr. Katherine Lemos, chairman and chief executive of the U.S. Chemical Safety and Hazard Investigation Board (CSB).

The system installed is a liquid nitrogen immersion-spiral freezer. This process occurs in two stages. In the first stage, the chicken travels on a conveyer belt and is submerged in liquid nitrogen at a temperature of -320F. In the second stage, the conveyer belt travels through the spiral freezer portion, and the chicken is exposed to recovered gaseous N (from stage 1), to complete the freezing process.

Schneider Bold

Investigators from the CSB arrived in Gainesville Thursday to begin the on-scene portion of our investigation into the liquid nitrogen release at the poultry facility.

The victims, all employees of Foundation Food Group in Gainesville, are Jose DeJesus Elias-Cabrera, 45; Corey Alan Murphy, 35; Nelly Perez-Rafael, 28; Saulo Suarez-Bernal, 41; Victor Vellez, 38; and Edgar Vera-Garcia, 28, the Hall County Sheriff’s Office said. In addition to the fatalities and hospitalizations, there were 130 evacuees. CSB officials also said two additional patients ended up released from the hospital, and a remaining patient, who was once in critical condition, is now in fair condition.

Hall County Sherriff, Gerald Couch, confirmed five employees died at the scene, and emergency personnel transported others to Northeast Georgia Medical Center. One of those employees died later at the hospital.

Jameel Fareed, one of roughly 130 employees evacuated from the plant Thursday morning, told Atlanta’s Channel 2 Action News the nitrogen leak set off chaos in the plant.

“First we just thought there was something wrong with the freezer, then they started saying get out,” Fareed said. “I just saw the fog and when I couldn’t see down the steps, I turned around. But I didn’t feel anything.”

Another worker said colleagues started pushing each other to get out.

In Plant 4, there are 5 production lines, and the event occurred on Line 4. On Line 4, workers process chicken to include seasoning, cooking, and then flash freezing.

Poultry plants use refrigeration systems that often include liquid nitrogen, which vaporizes into an odorless gas capable of displacing oxygen when leaked. Liquid nitrogen is colorless, odorless and extremely cold. It can cause serious damage and quick death with no warning. The gas can cause extensive tissue damage or burns. Inhaling large amounts of nitrogen can cause dizziness, nausea, vomiting, loss of consciousness and death.

For some reason not known yet, there was a release of liquid nitrogen, which rapidly converted to a gas. This gas is heavier than air, and forces oxygen out of the room, Lemos said.

In the facility, a cryogenic freezer and associated equipment houses and disperses the liquid nitrogen. However, the liquid nitrogen ends up stored in tanks external to the building, in the parking lot. The maintenance manager described personally closing the isolation valves of the tanks in the parking lot after the incident, shutting off supply to the building, which limited the potential damage for the event, Lemos said.

Investigators are currently working to understand the exact location of the point of release inside the plant, Lemos said. Plant 4 receives 2-3 18-wheel truckloads per day of liquid nitrogen.

It turns out the external and the interior elements of this system ended up manufactured by Messer. This includes the supply tanks outside, and the interior cryogenic freezing equipment on Line 4, the CSB reported Monday. As mentioned, major portions of the liquid nitrogen system, interior and exterior, ended up installed and commissioned in the last 4-6 weeks. In addition, investigators have reports that tools were on the ground around the equipment.