Dominion Energy Virginia application gained approval for an additional 20 years of operation for Surry Power Station Units 1 and 2, located near Surry, Virginia, expanding the renewed licenses authorizing reactor operation from 60 to 80 years.

Surry Unit 1’s subsequent renewed license expires on May 25, 2052, while Unit 2’s subsequent renewed license expires on Jan. 29, 2053, according to the approval from the Nuclear Regulatory Commission (NRC).

Each unit consists of a Westinghouse three-loop pressurized-water reactor with licensed thermal power of 2,587 megawatts thermal.

The rationale for the NRC’s decision is documented in the staff’s March 2020 final Safety Evaluation Report regarding the application, as well as the staff’s April 2020 final Supplemental Environmental Impact Statement.

The NRC Advisory Committee on Reactor Safeguards also reviewed the safety aspects of renewing the licenses. The state of Virginia provided its Coastal Zone Management Act certification for the review on April 1, 2021.

Schneider Bold

Dominion submitted the subsequent license renewal application on Oct. 15, 2018, for the Surry reactors, located approximately 17 miles northwest of Newport News, VA.

The subsequent license renewal process determines whether an operating reactor can extend its license for an additional 20 years (initial license renewals add 20 years to a reactor’s original 40-year license). Dominion’s application and environmental report, and supplemental information, minus proprietary details, are available on the NRC website.